Actual exam question from Scaled Agile's SAFe Scrum Master
Question #: 10
Topic #: 1
[All SAFe Scrum Master Questions]

Which of the following events aligns teams on a train?

  • A. PI Planning
  • B. Coach Sync
  • C. Architect Sync
  • D. Iteration Planning
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Tygrins
4 days, 20 hours ago
Selected Answer: A
Key Details About PI Planning: Purpose: Align teams on the train to a shared vision and plan for the upcoming Program Increment (typically 8–12 weeks).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago