What is one way uncommitted objectives help Agile Teams make a plan for the PI?

  • A. They generate additional ways to measure team progress
  • B. They maintain the predictability of achieving the objectives
  • C. They ensure the team has additional development options
  • D. They create an opportunity for teams to take on harder work
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
5f2650f
2 months, 2 weeks ago
Selected Answer: B
the answer is B Uncommitted objectives help improve the predictability of delivering business value since they are not included in the team’s commitment or counted against teams in the ART predictability measure. © Scaled Agile, Inc. Include this copyright notice with the copied content. Read the FAQs on how to use SAFe content and trademarks here: https://www.scaledagile.com/about/about-us/permissions-faq/
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago