exam questions

Exam SAFe Scrum Master All Questions

View all questions & answers for the SAFe Scrum Master exam

Exam SAFe Scrum Master topic 1 question 1 discussion

Actual exam question from Scaled Agile's SAFe Scrum Master
Question #: 1
Topic #: 1
[All SAFe Scrum Master Questions]

What is one benefit of having an IP iteration every PI?

  • A. It creates an estimating buffer for meeting PI objectives
  • B. It creates a chance for teams to manage quality
  • C. It creates a timeboxed opportunity for team growth
  • D. It creates a guardrail for teams working too hard
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AlinaHusanu
5 months ago
A is the correct answer
upvoted 1 times
...
techgeek9
10 months, 3 weeks ago
Correct answer is A based on sacledagileframework website.
upvoted 2 times
FunkyB
7 months, 3 weeks ago
Correct Answer: A It creates an estimating buffer for meeting PI objectives Innovation and Planning Iteration The Innovation and Planning (IP) Iteration is a unique, dedicated iteration that occurs every PI. It provides an estimating buffer for meeting PI Objectives and dedicated time for innovation, continuing education, PI Planning, and Inspect and Adapt (I&A) events. https://scaledagileframework.com/innovation-and-planning-iteration/
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.