Question #: 2
Topic #: 1
[All SAFe Product Owner-Product Manager Questions]

Which of the following events shows how well the ART is progressing toward meeting the PI Objectives?

  • A. PO Sync
  • B. Inspect and Adapt
  • C. Backlog Refinement
  • D. PI Planning
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
cmind911
6 months ago
Correct answer : A
upvoted 2 times
FunkyB
4 weeks ago
Correct answer : A Product Owner (PO) Sync The PO Sync is an ART event used to gain visibility into the ART’s progress toward meeting its PI objectives and to make any necessary adjustments. https://scaledagileframework.com/blog/glossary_term/po-product-owner-sync/
upvoted 1 times
...
...
santoshindia
7 months ago
Selected Answer: A
PO sync to check status
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago