During the PI Planning event, when are planning adjustments agreed upon?

  • A. During breakout sessions
  • B. During the draft plan review
  • C. During the management review and problem-solving
  • D. During Scrum of scrums
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
blue_moon
3 months, 1 week ago
https://scaledagileframework.com/pi-planning/ Management review and problem-solving – Draft plans likely present challenges like scope, people and resource constraints, and dependencies. During the problem-solving meeting, management may negotiate scope changes and resolve other problems by agreeing to various planning adjustments. © Scaled Agile, Inc. Include this copyright notice with the copied content. Read the FAQs on how to use SAFe content and trademarks here: https://scaledagile.com/about/about-us/permissions-faq/ Explore Training at: https://scaledagile.com/training/calendar/
upvoted 1 times
blue_moon
3 months, 1 week ago
Option C is the correct answer
upvoted 1 times
...
...
ashrmjoshi
5 months, 1 week ago
option C
upvoted 1 times
...
WhyRamy
6 months ago
C. During the management review and problem-solving
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago