Question #: 22
Topic #: 3
[All C_TS452_2021 Questions]

How can you completely block a material for procurement in a plant? (Choose two.)

  • A. Create an entry in the source list with a blocking indicator and NO supplier.
  • B. Create a blocking entry in the supplier master record.
  • C. Use a relevant plant-specific material status in the material master.
  • D. Create a quota arrangement entry with a quantity of zero.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
VIV2086
Highly Voted 1 year, 10 months ago
Selected Answer: AC
Set X plant material status in MM 80 or 90, and Using source list also a material can be blocked for purchasing. Supplier Master is irrelevant for this case as we are nit blocking a supplier
upvoted 6 times
...
ediibrah
Most Recent 1 year ago
Option B is incorrect because creating a blocking entry in the supplier master record does not block a specific material for procurement in a plant. Blocking a supplier/vendor account centrally in SAP can prevent both posting and order processing, but it applies to all materials associated with that supplier/vendor, not just a specific material. If you want to block a specific material for procurement, you can do so by creating an entry in the source list with a blocking indicator and no supplier, or by using a relevant plant-specific material status in the material master. Therefore, creating a blocking entry in the supplier master record is not a correct method to completely block a material for procurement in a plant
upvoted 1 times
...
AFM123
1 year, 6 months ago
Selected Answer: BC
b and c are correct
upvoted 2 times
...
praveenhp4
1 year, 9 months ago
Selected Answer: BC
vendor block and plant specific material status is sufficent for material block
upvoted 1 times
Vergok
1 year, 7 months ago
we want to block the material, regardless of the vendor used to purchase it, (if you block one vendor it doesn't stop it from being purchased by another) The answer is AC
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...