What are some advantages of a stock transport order compared to a stock transfer posting between two plants? (Choose three.)

  • A. You can create stock transport requisitions via MRP.
  • B. You can plan delivery costs.
  • C. You can post goods receipt in consignment.
  • D. You can issue from inspection stock.
  • E. You can post goods receipt to consumption.
Show Suggested Answer Hide Answer
Suggested Answer: ABC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
MLBME
Highly Voted 1 year, 11 months ago
it's not C but E, no?
upvoted 6 times
...
praveenhp4
Highly Voted 1 year, 9 months ago
ABE is the correct answer
upvoted 5 times
...
sharawi
Most Recent 9 months, 1 week ago
A,B & D are correct for D in delivery tab Stock type can be unrested, inspection quality and blocked - the business case for long transport you need to do another quality check or to put in blocked untill physical check and then release
upvoted 1 times
sharawi
9 months ago
D is incorrect, delivery tab for receipt in the destination plant not for issue from the source plant. E is correct
upvoted 1 times
...
...
ediibrah
1 year ago
Option C is incorrect because in a stock transport order, you cannot post goods receipt in consignment. In a consignment process, the goods are still owned by the supplier (consignor) and only change ownership when the recipient (consignee) consumes or sells the goods. This is different from a stock transport order where the ownership of the goods changes when the goods are issued from the supplying plant. Therefore, the goods receipt in a stock transport order cannot be posted in consignment
upvoted 2 times
...
Jewell_W
1 year, 2 months ago
ABE is the correct answer
upvoted 2 times
...
abeedfarooqui86
1 year, 3 months ago
Selected Answer: ABC
A. You can plan delivery costs. B. You can create stock transport requisitions via MRP. C. You can post goods receipt in consignment.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...