Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam C_TS462_2020 All Questions

View all questions & answers for the C_TS462_2020 exam

Exam C_TS462_2020 topic 2 question 12 discussion

Actual exam question from SAP's C_TS462_2020
Question #: 12
Topic #: 2
[All C_TS462_2020 Questions]

In which type of outline agreement would you see details of confirmed material quantities and delivery dates?

  • A. Quantity contract
  • B. Material-related value contract
  • C. Scheduling agreement
  • D. General value contract
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
UMESHKARANE
6 months, 1 week ago
Selected Answer: C
Scheduling agreement
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...