The technical completion of the current maintenance order was posted with a delay of 5 days. What happens to the next planned date if you set the shift factor for early completion to 100%?
For me, C is correct. The order was published with a delay of 5 days, which is why the change factor defined as early does not apply to this case. If it were a Shift factor late completion to 100% the correct answer would be B
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Nestor_OG
1 year, 1 month agoThwOutlawWarrior
1 year, 1 month ago