The technical completion of the current maintenance order was posted with a delay of 5 days.
What happens to the next planned date if you set the shift factor for early completion to 100%?

  • A. It is postponed by a full cycle (100%).
  • B. It is postponed by 5 days.
  • C. It is not shifted.
  • D. It will be 5 days earlier.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nestor_OG
1 year, 1 month ago
For me, C is correct. The order was published with a delay of 5 days, which is why the change factor defined as early does not apply to this case. If it were a Shift factor late completion to 100% the correct answer would be B
upvoted 3 times
...
ThwOutlawWarrior
1 year, 1 month ago
It should be B.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.