You want to assign components to an equipment task list. There is no BOM assigned to the equipment. What is the prerequisite for using the free assignment of material?
A.
Assign the header material of a material BOM to the equipment task list header.
B.
Assign the BOM usage for free assignment of material in Customizing.
C.
Assign the header material of a material BOM as assembly to a task list operation.
D.
Free assignment of material is always possible without any prerequisites.
To make a free material assignment, you must specify a BOM usage (generally used in Plant Maintenance) in Customizing (Control Data for Task List)
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
a50e462
8 months, 2 weeks agosye93
9 months, 4 weeks agoLeo_FsGT
1 year, 2 months ago