Exam C_TS413_2021 topic 1 question 9 discussion

Actual exam question from SAP's C_TS413_2021
Question #: 9
Topic #: 1
[All C_TS413_2021 Questions]

You create two maintenance packages and only one package should be executed at a time. Which parameter determines this?

  • A. Lead flow
  • B. Hierarchy
  • C. Cycle set sequence
  • D. Package sequence
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
85b45dd
8 months, 1 week ago
Is the answer for A meant to be Lead Float? If the question here is asking for how to take two orders called from unique packages that will call at the same time, but ensure they generate with staggered start and end dates, the initial and subs buffer, aka lead and subs float, can be used on the maintenance packages to manipulate the order dates. Hierarchy will supress one order, rather than stagger.
upvoted 1 times
...
sye93
9 months, 4 weeks ago
Hiearrchy
upvoted 3 times
...
Leo_FsGT
1 year, 2 months ago
Lead Flow just add number to start day, it's not de answer
upvoted 3 times
...
Leo_FsGT
1 year, 2 months ago
Selected Answer: B
Its B, Hierarchy
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...