You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time - key date. The orders should be called 3 months before the planned date. How can you set up the maintenance plan? (Choose two.)
If the duration of the cycle is 12 months and the call horizon is 0 %, 25%, 75%, or 100%, the system creates the order after the following number of days:
• 0% -> Immediate call
• 25% -> Call after 3 months, that is 25% of 12 months
•80% -> Call after 9 months, that is 75% of 12 months
•100% -> Call after 12 months, on the planned date
Addicionally if you select Day you can add 90 days, meand 3 months before the call.
Option C is correct
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Amol22
10 months ago85b45dd
8 months, 2 weeks agofilipsimovic3
10 months, 1 week agoMariorg
1 year agoanpang1910
1 year, 2 months agoLeo_FsGT
1 year, 2 months agoLeo_FsGT
1 year, 2 months ago