Question #: 99
Topic #: 1
[All Certified Business Analyst Questions]

Universal Containers uses Kanban to complete its Salesforce development. In the middle of a sprint, the sales manager submits an important item to the team.
What should the business analyst do next?

  • A. Ask the team to reprioritize the backlog and work on the Item at the top.
  • B. Ask the team to commit to the work for the next sprint.
  • C. Ask the team to pivot and complete the work immediately.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
sfreesway
10 months ago
Selected Answer: A
In Scrum you would say no and push it to the backlog for next sprint Kanban you can add it to the queue and work on it as the next highest task/item
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...