Exam Certified Business Analyst topic 1 question 47 discussion

Actual exam question from Salesforce's Certified Business Analyst
Question #: 47
Topic #: 1
[All Certified Business Analyst Questions]

The business analyst (BA) at Universal Containers (UC) wants to understand why UC failed to meet a deployment date for its product go live while following the Agile process. According to the BA's research, the developers lacked a sense of the work in progress and the intended goal of that work, and the QA team was unable to dearly test the functionality based on a given persona.
Which step should the BA take next?

  • A. Create a SWOT (strength, Weakness, Opportunity. Threat) analysis to understand why development and testing took more time.
  • B. Move the deployment date out so the teams have more time to work.
  • C. Review the user stories to ensure they are small, testable, and valuable.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Jude1337
Highly Voted 1 year, 7 months ago
Selected Answer: C
Should be "C". To me it seems he already did the SWAT "According to the BA's research, the developers lacked a sense of the work in progress and the intended goal of that work, and the QA team was unable to dearly test the functionality based on a given persona"
upvoted 5 times
...
Faheem13
Most Recent 1 year, 5 months ago
looks like B
upvoted 1 times
scopic
1 year, 1 month ago
Quit guessing
upvoted 6 times
...
...
DuyNg
1 year, 8 months ago
The correct choice is C: "Review the user stories to ensure they are small, testable, and valuable." The scenario indicates issues with the developers understanding the work required and QA testing effectively. This suggests the user stories were not adequately clear or detailed. Reviewing the user stories to ensure they meet core criteria like being small, testable, and delivering value would help address the root causes of the delays and missed deadline. A SWOT analysis could be useful to understand broad issues, but would not directly address poorly defined user stories. Moving the deadline without fixing underlying issues would likely just lead to more delays or problems. So focusing on user story quality is the best step to resolve the challenges described and prevent them in the future.
upvoted 3 times
...
givagr
1 year, 8 months ago
Deployment date has already been missed. Reviewing the user stories will not help understand what went wrong.
upvoted 2 times
...
jimhatway22
1 year, 9 months ago
why not A ?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.