DRAG DROP -

PLANS -
The project manager is preparing the stage 3 plan and has asked the team manager for the 'amended course booking procedures' work package to prepare the team plan at the same time.
Here are three actions that will need to be carried out when preparing these plans.
Which role (A-F) should be responsible for each action?
Choose only ONE role for each action. Each role can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Project support, senior user, team manager
upvoted 1 times
...
RGohel
1 year, 2 months ago
1. Project support 2. Senior User 3. Team manager Ref: 9.2.2 page 101
upvoted 1 times
...
MortenC
1 year, 9 months ago
First:Project support 7.2.1.9 Second: Senior User? Third: Team Manager?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...