Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

  • A. Controlling a Stage
  • B. Closing a Project
  • C. Directing a Project
  • D. Managing a Stage Boundary
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
The process that provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification is D. Managing a Stage Boundary.
upvoted 2 times
...
Nabin55555hhhjj
1 year, 9 months ago
Selected Answer: D
D is answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...