Exam PRINCE2-Practitioner topic 11 question 20 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 20
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -
The project is in stage 2. The project manager has heard that a competitor may launch a similar e-learning course much sooner than ABC Company. There is a threat that the earlier launch of a competitor's course may reduce the profitability of ABC Company training courses.
Here are three responses to this risk.
Which risk response type (A-F) are they?
Choose only one response type for each risk response. Each response type can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
11 months, 2 weeks ago
As per other sources, the correct answer is - 1) Accept the Risk. 2) Reduce a threat. 3) Accept the risk.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
1. Prepare contingent plan By preparing a contingent plan, you are taking proactive measures to address any potential threats or opportunities that may arise from monitoring your competitor's activities. This allows you to be prepared for various scenarios and take appropriate actions as needed. 2.Reduce a threat. Delivering the product course earlier than originally planned can be seen as a threat because it could potentially impact the quality of the course or strain resources. The strategy to “reduce a threat” involves taking action to minimize the probability of the event occurring, or reduce its impact if it does occur 3.Accept the risk. In this scenario, the belief that the products are of the highest quality and the decision to continue with the project as planned indicates a willingness to accept the risk. This means that no proactive action is taken to address the risk, but rather, it is accepted and monitored. If the risk materializes, then reactive action will be taken as necessar
upvoted 2 times
ManikRoy
1 year, 1 month ago
Agree with this answer.
upvoted 1 times
...
...
Duribaci
1 year, 8 months ago
1st and 3rd should be just accept in my opinion...
upvoted 2 times
...
MortenC
1 year, 9 months ago
Why Reduce Threath? They are doing nothing....
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...