The development of the 'e-learning course' will be outsourced to an external supplier and their key members will join the project management team. The supplier wants to keep their work processes confidential and not share these with ABC Company. ABC Company has agreed.
Who should approve the external supplier's team plan?

  • A. Senior supplier
  • B. Project manager
  • C. Supplier assurance
  • D. Corporate, programme management or customer
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ppp333
9 months ago
In PRINCE2, if the project management team includes key members from an external supplier, the approval of the supplier's team plan would typically be the responsibility of Corporate, Programme Management, or the Customer roles, depending on the specific governance structure of the organization and the project. These roles are responsible for overseeing the project at a higher level and ensuring that it aligns with organizational objectives and standards. Therefore, the correct answer is: D. Corporate, programme management or customer
upvoted 1 times
...
ManikRoy
1 year, 2 months ago
Refer 18.4.1 Seek necessary approval for the team plan (although in a commercial customer/supplier relationship it may be inappropriate for the project manager to review and approve the team plan and, in such a context, the senior supplier may review and approve the team plans).
upvoted 1 times
...
ravi_aws
1 year, 2 months ago
The project manager reviews team plans for the internal project organization, but not third-party suppliers. Supplier assurance provides objective assessment, but does not approve team plans. Corporate/programme/customer are outside the project and would not approve team plans.
upvoted 1 times
...
Carpediempyy
1 year, 3 months ago
senior supplier is inhouse, would have conflict of interest with the external supplier, same with C. I think D makes sense?
upvoted 1 times
...
KPBGBAP
1 year, 10 months ago
Selected Answer: A
Senior Supplier. Corporate and program management is incorrect answer
upvoted 4 times
...
Ubercool
1 year, 11 months ago
18.4.1 Accept a work package Seek necessary approval for the team plan (although in a commercial customer/supplier relationship it may be inappropriate for the project manager to review and approve the team plan and, in such a context, the senior supplier may review and approve the team plans). A. Senior Supplier
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago