Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 8 question 2 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 2
Topic #: 8
[All PRINCE2-Practitioner Edition 6 Questions]

During which process would the stage tolerances be set?

  • A. Controlling a Stage
  • B. Initiating a Project
  • C. Managing a Stage Boundary
  • D. Directing a Project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
4 months ago
Selected Answer: B
During the "Initiating a Project" process, the detailed planning of the project is conducted, which includes setting up the project controls and tolerances. This process involves defining the project's scope, objectives, and how it will be controlled and governed. Part of this involves setting the tolerances for each stage, which are agreed upon to ensure that the project stays on track and within acceptable limits. The other options are not correct because: A. Controlling a Stage: This process involves managing and monitoring the day-to-day activities within a stage, not setting tolerances. C. Managing a Stage Boundary: This process is about reviewing the current stage and planning for the next stage, but the tolerances would already have been set during the initiation. D. Directing a Project: This process is about the Project Board providing overall direction and decision-making but not specifically about setting stage tolerances. Thus, stage tolerances are established during the "Initiating a Project" process to provide clear guidelines for project execution and control.
upvoted 1 times
...
HelgeFFM
10 months ago
Selected Answer: D
I would also say D as it asked for PHASE tolerences.
upvoted 1 times
...
ManikRoy
1 year, 1 month ago
Selected Answer: D
Stage tolerances are set by Project Board under the 'Directing a Project' process. (refer 15.4.3)
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B During the "Initiating a Project" process, one of the key activities is to define the project controls, including the setting of tolerances.
upvoted 1 times
...
SantiagoAregentina
1 year, 2 months ago
Selected Answer: B
It is "B". Ref 16.4.6 Set up the project controls
upvoted 1 times
...
PrincessOfHess
1 year, 9 months ago
It is D (15.4.3)
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...