In structured project management frameworks like PRINCE2, the Project Board is responsible for the overall direction and management of the project within the set tolerances. If tolerances are threatened, it indicates a significant deviation that may affect the project's objectives, and this requires the attention and decision-making authority of the Project Board. The Project Board can then decide on the necessary corrective actions or escalate the issue further if needed.
Options B (Project Manager) and D (Executive) are not correct because, while the Project Manager is responsible for day-to-day management and the Executive is a key member of the Project Board, it is the Project Board as a whole that needs to be informed and take action on tolerance breaches. Option C (Corporate or Programme Management) is also not the immediate next step unless the Project Board decides to escalate the issue further.
A) as per 12.2.1 => if any forecast indicate that the project is likely to exceed the agreed project tolerances, then the deviation should be referred to corporate, programme management or the customer _by the project board_... so the first one to be notified is the Project Board...
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
mcesarlara
4 months agoMcDope
5 months, 1 week agoPrincessOfHess
1 year, 9 months ago