Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 7 question 8 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 8
Topic #: 7
[All PRINCE2-Practitioner Edition 6 Questions]

The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2.
Is this an appropriate action, and why?

  • A. Yes, because the project manager should recommend corrective actions required.
  • B. Yes, because moving the work enables stage 2 to be delivered within tolerance.
  • C. No, because the team manager should inform the project manager by raising an issue.
  • D. No, because the stage deviation should be referred to the project board for a decision.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://www.prince2primer.com/project-board-and-project-manager-prince2-controls/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SantiagoAregentina
1 year, 2 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
PrincessOfHess
1 year, 10 months ago
It is D (15.4.3)
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...