Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 88 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 88
Topic #: 1
[All PRINCE2-Foundation Questions]

How many management stages should a PRINCE2 project consist of?

  • A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  • B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  • C. Initiation stage and at least one other management stage to cover the remainder of the project
  • D. Start up stage, initiation stage and a closing stage
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
HMZ09
2 weeks, 2 days ago
There are a minimum of two management stages in a project: the Initiation Stage and one further Management Stage. The Closing a Project process is then the last part of the 2nd Stage in a two-stage project. A PRINCE2 project is planned, monitored and controlled on a stage-by-stage basis.
upvoted 1 times
...
dgk
3 weeks, 6 days ago
Selected Answer: B
In PRINCE2, a project must have at least two management stages: • an initiation stage • at least one further management stage. The more complex and risky a project is, the more management stages will be required.
upvoted 2 times
...
Laserboy
3 months, 3 weeks ago
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage In PRINCE2, a project typically consists of the following stages: Start-up stage: To initiate the project and prepare for the detailed planning. Initiation stage: To establish the project's foundation, including the Project Initiation Documentation (PID). Management stages: At least one or more management stages to cover the remainder of the project. The number of these stages depends on the project's size and complexity. Closing stage: To formally close and review the project. Therefore, a PRINCE2 project will always include the start-up stage, at least one management stage, and a closing stage.
upvoted 1 times
...
FlyingDutch
1 year, 10 months ago
Selected Answer: C
C is correct. there should be at least 2 stages within a project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...