Exam PRINCE2-Foundation topic 1 question 121 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 121
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the Risk theme?

  • A. Establish a method for the implementation of continuous improvement during the project
  • B. Identify, assess and control problems that have occurred
  • C. Provide the Project Board with a time-driven control to capture all project risks
  • D. Establish a cost-effective procedure to identify, assess and control risks
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
omande
1 year, 1 month ago
Selected Answer: D
Uncertainties relate more to the concept of risk than problem. Therefore the correct answer should be D.
upvoted 1 times
...
Firey
1 year, 4 months ago
The purpose of the Risk theme in project management is to identify, assess, and control risks that may affect the project's objectives. A risk is an uncertain event or condition that, if it occurs, can have a positive or negative effect on the project. The Risk theme provides a systematic and proactive approach to risk management to ensure that risks are identified and managed before they become issues.
upvoted 1 times
...
LAVAZ
1 year, 9 months ago
The text clearly states; the purpose of the risk theme is to identify, asses and control uncertainty and, as a result, improve the ability of the project to succeed. The answer should be B
upvoted 1 times
Ausias18
1 year, 4 months ago
It is not B, as B says: Identify, assess and control problems that have occurred, Problems that have occurred are issues not risks. Ans is C
upvoted 2 times
Ausias18
1 year, 4 months ago
Ans is D, sorry, I was fed up by the answer of LAVAZ...
upvoted 2 times
...
...
...
MQ273
1 year, 10 months ago
Correct answer should be B! Purpose of risk theme is to identify , assess, and control uncertainty, and as a result, improve the ability of the project to succeed.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.