Exam PRINCE2-Practitioner topic 3 question 12 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 12
Topic #: 3
[All PRINCE2-Practitioner Edition 6 Questions]

During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan.
Is this an appropriate application of the plans theme, and why?

  • A. Yes, because detailed planning of stage 3 should take place after completion of the stage 2 products.
  • B. Yes, because risk planning should take place in the stage plan before the risks occur, not in the project plan.
  • C. No, because the risks inherent in the project plan should be assessed, and the plan modified to manage them.
  • D. No, because the risk actions to manage project-level threats should be recorded in the risk register.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
https://books.google.com.pk/books?id=CSm7x74Px94C&pg=PA181&lpg=PA181&dq=prince2+risks+inherent+in+the+project+plan+should+be
+assessed,+and+the+plan+modified+to+manage+them&source=bl&ots=wY57bkzn3M&sig=ACfU3U2SjvwFX9KajLooA41PHyOT8- nHAA&hl=en&sa=X&ved=2ahUKEwjwk9b1ybnhAhWhMewKHWLwCQYQ6AEwCXoECAgQAQ#v=onepage&q=prince2%20risks%20inherent%20in%20the%
20project%20plan%20should%20be%20assessed%2C%20and%20the%20plan%20modified%20to%20manage%20them&f=false

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 2 months ago
Selected Answer: C
Refer 9.3.1.7 After the plan has been produced, it should still be considered a draft until the risks inherent in the plan have been identified and assessed, and the plan possibly modified. Though option D is true, but it mentions about risk actions not the identified risk itself.
upvoted 1 times
...
MEHREEN1985
1 year, 8 months ago
9.3.1.7
upvoted 2 times
...
PrincessOfHess
1 year, 10 months ago
C (10.2.)
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...