Question #: 434
Topic #: 1
[All PRINCE2-Foundation Questions]

Which action should the project manager take during the ‘assessing issues’ step?

  • A. Create an exception plan for project board approval
  • B. Gain project board feedback on the issue priority
  • C. Consider the impact of alternative options for resolution
  • D. Determine the initial priority of the issue that has been raised
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
skillfulsatellite
1 day, 12 hours ago
Selected Answer: C
C. Consider the impact of alternative options for resolution In this step, the project manager assesses the issue and considers various options to resolve it, including evaluating their potential impacts on the project’s scope, cost, quality, and schedule. This ensures that the best resolution approach is chosen before escalating or taking further actions.
upvoted 1 times
...
Examcollectorthanos
6 days, 6 hours ago
C is correct; Why other options are not the primary focus of this step: A. Create an exception plan for project board approval: Exception plans are created when tolerances are exceeded, not for every issue. B. Gain project board feedback on the issue priority: While the project board might be consulted, the project manager is responsible for the initial assessment. D. Determine the initial priority of the issue that has been raised: This is usually done when the issue is first identified, before the detailed assessment.
upvoted 1 times
...
Myname
1 year, 4 months ago
Option B is correct as per the contents in Prince2 6th Edition pocket Guide
upvoted 1 times
...
Risto83
1 year, 11 months ago
D 11.4.2 Assessing issues It may be necessary to request advice from the project board to check its understanding of the issue’s priority or severity before proposing resolutions
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...