Why does the project board review the PID during an end stage assessment?

  • A. To confirm that project controls are adequate for the remainder of the project
  • B. To notify the commissioning organization that the project has been authorized
  • C. To review summarized progress to date and decide what to do next with the project
  • D. To ensure that post project reviews of operational performance are planned
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
skillfulsatellite
1 day, 12 hours ago
Selected Answer: A
During an end stage assessment, the project board reviews the Project Initiation Documentation (PID) to ensure that: The overall approach to the project remains valid. The controls, governance, and strategies outlined in the PID are still appropriate and effective for the remaining stages of the project.
upvoted 1 times
...
Examcollectorthanos
5 days, 9 hours ago
A; please change this is confusing; During an End Stage Assessment, the Project Board reviews the Project Initiation Documentation (PID) to ensure that the overall project management controls (e.g., governance, plans, and tolerances) remain adequate and relevant for the remainder of the project. The PID is a baseline document that defines how the project will be managed and controlled, and it must be revisited at key points to ensure it is still appropriate.
upvoted 1 times
...
Kjennset
3 weeks, 2 days ago
Selected Answer: A
During an end stage assessment, the Project Board reviews the Project Initiation Documentation (PID) to ensure that the current project controls are still suitable and will remain effective for the rest of the project. This review helps confirm that any necessary changes in governance, risk management, or control processes are addressed before the project moves into the next stage.
upvoted 1 times
...
Sniperone
1 year, 11 months ago
Selected Answer: A
A is Correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...