Exam PRINCE2-Foundation topic 1 question 437 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 437
Topic #: 1
[All PRINCE2-Foundation Questions]

Which theme establishes the mechanisms to control against baselines by providing a forecast for the project’s objectives and continued viability?

  • A. Business case
  • B. Plans
  • C. Change
  • D. Progress
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
skillfulsatellite
1 day, 12 hours ago
Selected Answer: D
The Progress theme focuses on monitoring and controlling project performance, ensuring that it stays within agreed tolerances (such as time, cost, and quality), and forecasting future performance to ensure that the project can achieve its objectives and remain viable.
upvoted 1 times
...
Kjennset
3 weeks, 2 days ago
Selected Answer: D
The 'Progress' theme in PRINCE2 provides mechanisms to control the project against baselines by monitoring and forecasting the project's objectives and continued viability. This theme enables the project team to evaluate current performance, assess future projections, and determine whether the project remains viable and aligned with its objectives. Through progress reports, stages, and tolerances, the Project Board and Project Manager can make informed decisions about the project's future.
upvoted 1 times
...
bes_i
4 months ago
Selected Answer: D
D is correct
upvoted 2 times
...
Myname
1 year, 4 months ago
The correct answer is Option D. Progress theme contents are pretty clearly articulated
upvoted 1 times
...
Risto83
1 year, 11 months ago
The purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and the project’s continued viability, and control any unacceptable deviations.
upvoted 2 times
...
Risto83
1 year, 11 months ago
D 12.1 The progress theme
upvoted 1 times
...
Ro96
1 year, 11 months ago
Selected Answer: A
Should be A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...