Which theme establishes the mechanisms to control against baselines by providing a forecast for the project’s objectives and continued viability?

  • A. Business case
  • B. Plans
  • C. Change
  • D. Progress
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
bes_i
2 months, 4 weeks ago
Selected Answer: D
D is correct
upvoted 1 times
...
Myname
1 year, 3 months ago
The correct answer is Option D. Progress theme contents are pretty clearly articulated
upvoted 1 times
...
Risto83
1 year, 9 months ago
The purpose of the progress theme is to establish mechanisms to monitor and compare actual achievements against those planned, provide a forecast for the project objectives and the project’s continued viability, and control any unacceptable deviations.
upvoted 2 times
...
Risto83
1 year, 9 months ago
D 12.1 The progress theme
upvoted 1 times
...
Ro96
1 year, 10 months ago
Selected Answer: A
Should be A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...