D is correct; The other options are not the primary purpose of this theme:
A. To ensure that the change control approach is appropriate for the size of the project: This is related to the "change" theme.
B. To ensure that themes can be applied using techniques that are appropriate to the project: This is related to the "tailor to suit the project" principle.
C. To ensure that responsibilities are defined for directing, managing and delivering the project: This is related to the "organization" theme.
D is correct. Progress is the measure of the achievement of the objectives of a plan. Controlling progress is central to project management, ensuring that the project remains viable against its approved business case.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days agoameli8222
1 year, 7 months agoRo96
1 year, 11 months ago