Question #: 361
Topic #: 1
[All PRINCE2-Foundation Questions]

What should be included in the PID as a minimum requirement for managing organization?

  • A. Definition of the training required throughout the project
  • B. Documentation of the project management team structure
  • C. An analysis of the power and influence of the major stakeholders
  • D. A description of the customer's quality expectations
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://prince2.wiki/management-products/project-initiation-documentation/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ro96
1 year, 11 months ago
Selected Answer: B
Per https://prince2.wiki/management-products/project-initiation-documentation/ B: Quality Criteria for PID: The project management team (PMT) structure is complete, with names, titles, links to role descriptions and some indication that people are aware of their roles.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...