What is the first task of product-based planning?

  • A. Produce the Initiation Stage Plan
  • B. Write the Project Product Description
  • C. Identify dependencies
  • D. Create the product breakdown structure
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ryou100
2 years ago
PRINCE2 uses the technique Product-Based planning to identify and analyze the planned products. The four steps in Product-Based Planning are: 1. Writing the Project Product Description 2. Creating the product breakdown structure 3. Writing the Product Description 4. Creating the Product Flow Diagram
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...