The Health and Safety Training Project is a critical project within a programme. Due to resource constraints within the programme, the programme manager has been appointed as both executive and project manager of the Health and Safety Training Project.
Is this an appropriate action, and why?
kuku1789
2 years, 1 month agokuku1789
2 years, 1 month ago