Question #: 20
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

The Health and Safety Training Project is a critical project within a programme. Due to resource constraints within the programme, the programme manager has been appointed as both executive and project manager of the Health and Safety Training Project.
Is this an appropriate action, and why?

  • A. Yes, because the programme manager can ensure that the project is aligned to the programme outcomes
  • B. Yes, because the programme manager can be appointed as executive of the programme's projects
  • C. No, because the programme manager's role should remain separate from that of the project's executive
  • D. No, because the role of executive and project manager should remain separate for governance reasons
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kuku1789
2 years, 1 month ago
it is B (The programme manager may be the executive for one or more of the projects)
upvoted 1 times
kuku1789
2 years, 1 month ago
D is correct
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other