Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 21 question 15 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 15
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

During stage 3 the project manager authorizes the work package for the 'marketed courses'. The project manager and internal marketing team manager agreed that the course should be marketed in a minimum of three trade magazines, and a maximum of five, by the end of stage 3.
Which principle is being applied, and why?

  • A. 'Manage by exception', because the project manager should set tolerances for the scope of the products to be delivered
  • B. 'Manage by exception', because the project manager should set tolerances for the quality of the products to be delivered
  • C. 'Defined roles and responsibilities', because the internal marketing team need to understand what they need to deliver and when
  • D. 'Defined roles and responsibilities', because suppliers can be either internal or external to ABC Company
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
4 months ago
Is option A the most appropriate as it focuses on the principle of "manage by exception", highlighting the importance of establishing clear tolerances for the scope of products to be delivered?
upvoted 1 times
...
HelgeFFM
10 months ago
Selected Answer: C
this is a trick question. If you look at table 12.1, there is only one scope example mentioned in the book mentionend as a tolerance for scope and that is Moscow. So this is in my opinion not about the tolerances but about the defined roles and responsitiblities. That makes C the correct answer.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Manage by exception', because the project manager should set tolerances for the scope of the products to be delivered
upvoted 2 times
...
kuku1789
2 years, 1 month ago
it is A
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...