Question #: 4
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

MANAGING A STAGE BOUNDARY -
At the end of stage 3, the pilot courses have been planned and this work revealed that sales of the health and safety training course were expected to be higher than originally expected. Therefore, the project manager revised the sales forecast for the course. This revised forecast needs to be both reviewed and approved.
Who should review this forecast after it has been updated as part of the 'update the business case' activity?

  • A. ABC Company's board of directors including the Chief Executive Officer
  • B. The Business Development Director who is the executive
  • C. The Operations Director who is the senior user
  • D. The team manager for the 'delivered pilot courses' work package
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.prince2.com/uk/prince2-business-case#:~:text=During%20the%20project%2C%20a%20PRINCE2,it%20should%20be%20done%20now

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The Business Development Director who is the executive
upvoted 1 times
...
kuku1789
2 years, 1 month ago
it is B
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...