DRAG DROP -
DIRECTING A PROJECT -
Here are three actions that are carried out as part of the 'directing a project' process.
During which activity (A-E) should they be carried out?
Choose only one activity for each action. Each activity can be used once, more than once, or not at all.
Select and Place: