Question #: 5
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

Towards the end of stage 2, the stage 3 plan is being prepared. This includes the work required to promote the new courses to other training companies. In addition to the current ways of marketing the courses, the Sales Director wants to advertise in trade magazines. The likely costs involved and the opportunities it may bring have been identified.
As part of the 'update the project plan' activity, what should the project manager be responsible for?

  • A. Creating time and cost tolerances for the delivery of the magazine advertisements.
  • B. Creating the product description, with detailed quality criteria, for the magazine advertisements.
  • C. Recording the effect of implementing the magazine advertisements on the overall time and cost of the project.
  • D. Recording changes to ABC Company risk appetite as a result of using the magazine advertisements.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: C
Ref 19.4.2 The project plan is updated to incorporate actual progress from the management stage that is finishing, and to include forecast duration and costs from the exception plan or stage plan for the management stage about to begin.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Creating time and cost tolerances for the delivery of the magazine advertisements [A] is not relevant to this activity, as tolerances are set during the 'create the project plan' activity. Creating the product description, with detailed quality criteria, for the magazine advertisements [B] is not relevant to this activity, as the product description is created during the 'create the project plan' activity. Recording changes to ABC Company risk appetite as a result of using the magazine advertisements [D] is not relevant to this activity, as changes to risk appetite are recorded during the 'update the risk register' activity. Therefore, the appropriate action for the project manager during the 'update the project plan' activity is to record the effect of implementing the magazine advertisements on the overall time and cost of the project.
upvoted 1 times
ravi_aws
1 year, 1 month ago
C is the best option
upvoted 1 times
...
...
Ubercool
1 year, 9 months ago
A is correct - part of updating the Project Plan B is part of updating the Product Description
upvoted 1 times
...
schris
2 years, 1 month ago
Shouldn't this be a B?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...