During stage 4, a work package was authorized for the 'delivered pilot courses' to be completed by the end of week 2. The 'finalized materials' work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses.
During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2.
Should the team manager have reported this delay previously as an issue, and why?
ManikRoy
1 year, 1 month agoravi_aws
1 year, 1 month agoM477001
1 year, 7 months agoMEHREEN1985
1 year, 8 months agoschris
2 years, 1 month ago