Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 1 question 9 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 9
Topic #: 1
[All PRINCE2-Practitioner Edition 6 Questions]

During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course.
The change to project scope was approved and the cost of ֲ£2,500 was paid for from the change budget. The project manager documented an increase of ֲ£2,500 in the project budget in the business case.
Is this an appropriate action, and why?

  • A. Yes, because the justification for the project should be recalculated based on the revised project budget.
  • B. Yes, because the project manager determines which costs need to be updated at the end of each stage
  • C. No, because the use of the change budget means that the project budget does not need to be increased.
  • D. No, because changes to operational costs post-project should have been included in the business case.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
11 months, 2 weeks ago
Selected Answer: C
C. No, because the use of the change budget means that the project budget does not need to be increased.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The change budget is specifically set aside for unforeseen changes that might occur during the project. When a change is approved and paid for from the change budget, it does not necessitate an increase in the project budget. The project budget is typically a forecast of the costs associated with the planned scope of the project, while the change budget is a reserve for unplanned changes.
upvoted 1 times
...
ManikRoy
1 year, 2 months ago
I think it should be option B as the project manager need to update the business case with updated cost at the end of each management stages. And I believe the change budget is part of the project budget!
upvoted 1 times
ManikRoy
1 year, 1 month ago
Sorry now get it, the primary project budget includes change budget, so the project budget remain unchanged.
upvoted 1 times
...
...
georgio1974
1 year, 3 months ago
Selected Answer: C
agree it is C, the primary project budget is not affected as the change budget has been used
upvoted 2 times
...
PieroBe
1 year, 4 months ago
It is C as project budget includes change budget so no need to rise the project budget
upvoted 1 times
...
mogasser
1 year, 4 months ago
Selected Answer: C
Answer C (Unpopular objective answer/open for discussion) Ref. 9.3.1.5 "The budget should include: Cost of activities; Risk budget; Change budget; Cost tolerance" Ref. 11.3.6 " Including a change budget provides for a more realistic expectation of the overall costs/timeframe of the project."
upvoted 1 times
YogenS
10 months ago
Hi, Can you explain please how and where to look for the reference -you provided? i.e. Ref. 9.3.1.5 and Ref. 11.3.6.... sorry for sounding to childish but I didn't get it
upvoted 1 times
...
...
Yanju
1 year, 10 months ago
It should be A
upvoted 1 times
...
gregrobo
1 year, 12 months ago
i think this is A ? No ?
upvoted 1 times
...
schris
2 years, 1 month ago
Does somebody know why it is not A, but B? Thank you in advance!
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...