Question #: 49
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

ABC Company produces a corporate business plan which includes the targets for the next 12 months. For the Health and Safety Training Project, a feasibility study was carried out and, as a result, the expected sales were included in this plan. During the 'starting up a project' process, the executive advised the project manager that the corporate business plan provides sufficient justification to initiate the project.
Is this a correct application of the 'continued business justification' principle, and why?

  • A. Yes, because the executive is responsible for the project's continued business justification.
  • B. Yes, because the business justification needs to be recorded and approved in some form.
  • C. No, because the feasibility study provides sufficient business justification for the project.
  • D. No, because business justification is not required until the 'initiating a project' process.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: B
Agree with others in the comment section that B seems to be the most appropiate of all options.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
A is incorrect because the executive alone can't justify the project. C is incorrect because other documents can provide the justification. D is incorrect because some form of justification is required for startup. Therefore, B is the best answer. The corporate plan's approval fulfills the need for documented justification according to the principle.
upvoted 1 times
...
Carpediempyy
1 year, 2 months ago
When I read this I thought it was B "In most organizations the business justification is usually documented in some form of business case. " but Its A, bcs of this, PRINCE2 requires that for all projects: •there is a justifiable reason for starting the project •that justification is recorded and approved •the justification remains valid, and is revalidated, throughout the life of the project.
upvoted 1 times
...
mogasser
1 year, 4 months ago
Selected Answer: B
I believe it's B, based on 3.1 page 21
upvoted 2 times
...
MortenC
1 year, 9 months ago
Selected Answer: B
3.1 page 21
upvoted 2 times
...
MortenC
1 year, 9 months ago
Check 7.2.1.10
upvoted 1 times
MortenC
1 year, 9 months ago
wrong reference...please delete
upvoted 1 times
...
...
ameyaengg
2 years, 2 months ago
Correct Answer : C
upvoted 1 times
ameyaengg
2 years, 2 months ago
Sorry TYPO : correct answer is B
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...