The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the 'recommended project closure' activity.
Is this appropriate, and why?
Ppp333
8 months agonazzzzzzzzz
1 year agoManikRoy
1 year, 1 month agoManikRoy
1 year, 1 month agoravi_aws
1 year, 1 month agoCarpediempyy
1 year, 2 months agoCarpediempyy
1 year, 2 months agoameyaengg
2 years, 2 months ago