Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 199 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 199
Topic #: 1
[All PRINCE2-Foundation Questions]

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

  • A. A description of the risk management procedure
  • B. An explanation of the company's risk appetite
  • C. The names of the assigned actionees for each risk
  • D. Estimations of the likelihood and impact of risks
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://www.prince2primer.com/prince2-2017-risk-theme-changes/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
KeanoD
2 years, 3 months ago
Information about all project risks are maintained in a risk register, and a risk management approach is written to outline the general approach to risk management during the project. Included in this approach is a description of the risk management procedure.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel