funding for the Change Authority typically comes from the overall project budget rather than a change budget specifically allocated for changes in scope.
Change budget = The money allocated to the change authority available to be spent on authorized requests for change
Change authority = A person or group to which the project board may delegate responsibility for the consideration of requests for change or off-specifications. The change authority may be given a change budget and can approve changes within that budget
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
am156
7 months agobdb1993
8 months, 1 week agoTRIJB
8 months, 1 week agoomande
1 year, 8 months agofaileru
2 years, 8 months ago