funding for the Change Authority typically comes from the overall project budget rather than a change budget specifically allocated for changes in scope.
Change budget = The money allocated to the change authority available to be spent on authorized requests for change
Change authority = A person or group to which the project board may delegate responsibility for the consideration of requests for change or off-specifications. The change authority may be given a change budget and can approve changes within that budget