Which should be provided by a project mandate?

  • A. Terms of reference
  • B. Detailed Business Case
  • C. Stage tolerances
  • D. Initiation Stage Plan
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 2 years, 6 months ago
14.3 Context: The project mandate should provide the terms of reference for the project and should contain sufficient information to identify at least the prospective executive of the project board. The mandate is refined to develop the project brief.
upvoted 5 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...