Question #: 33
Topic #: 1
[All PRINCE2-Foundation Questions]

Who should act as the communication channel between a project and corporate or programme management?

  • A. Project Board
  • B. Project Assurance
  • C. Project Manager
  • D. Project Support
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
3578791
1 week, 4 days ago
C. Project Manager In PRINCE2, the Project Manager is the person responsible for day-to-day management of the project and acts as the main communication channel between the project and corporate or programme management. They are responsible for ensuring that the project aligns with organizational objectives and that any issues or updates are communicated to the higher levels of management (the Project Board, corporate, or programme management).
upvoted 1 times
...
Firey
1 year, 4 months ago
The project board also acts as a communication channel or interface with corporate management.
upvoted 1 times
...
Isabaut
2 years, 6 months ago
Selected Answer: A
Project Board is correct
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted