Which is an objective of the Initiating a Project process?

  • A. Develop the corporate quality management system as part of the Project Initiation Documentation
  • B. Prepare the plans for the subsequent stages
  • C. Summarize how the organization's project management method will be tailored for the project
  • D. Request authority from corporate management to deliver the project
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
2 years, 6 months ago
C is correct: 16.2 How the corporate, programme management or customer method will be tailored to suit the project.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...