exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 399 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 399
Topic #: 1
[All PRINCE2-Foundation Questions]

How should the 'managing a stage boundary' process be used towards the end of a project's final delivery stage?

  • A. To plan the activities of the 'closing a project process
  • B. To implement any exception plan requests from the project board
  • C. To create a benefits management approach for corporate, programme management or the customer
  • D. To review an issue received from a team manager
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
skillfulsatellite
1 month, 1 week ago
Selected Answer: A
Towards the end of a project's final delivery stage, the 'managing a stage boundary' process is used to review the progress of the project and plan for the closing of the project. This includes ensuring that all final activities, such as the formal closure and review of project benefits, are planned and prepared for a smooth transition to project closure.
upvoted 1 times
...
Examcollectorthanos
1 month, 2 weeks ago
A is correct; Why the other options are less suitable: B. To implement any exception plan requests from the project board: Exception plans are usually handled within a stage, not at the boundary of the final stage. C. To create a benefits management approach for corporate, programme management, or the customer: The benefits management approach should be created much earlier in the project, during initiation. D. To review an issue received from a team manager: Issues should be managed as they arise, not deferred to the end of the final stage.
upvoted 1 times
...
Kjennset
1 month, 4 weeks ago
Selected Answer: A
The 'Managing a Stage Boundary' process is used to prepare for the transition from one stage to the next, and in the context of the final delivery stage, it includes planning the activities necessary for the 'Closing a Project' process. This involves reviewing the progress and performance of the project, ensuring that all deliverables are complete, and preparing the necessary documentation and actions to formally close the project.
upvoted 1 times
...
bes_i
5 months, 1 week ago
Selected Answer: A
A. To plan the activities of the 'closing a project' process The 'Managing a Stage Boundary' process involves planning and preparing for the transition from one stage to the next, or in this case, preparing for the project's closure. This includes updating the Project Plan, reviewing the project's progress, and ensuring that all activities necessary for closing the project are planned and managed effectively. By doing this, the project ensures a smooth transition to the 'Closing a Project' process, which involves finalizing the project deliverables, ensuring all objectives have been met, and formally closing the project.
upvoted 1 times
...
Zarini
10 months, 2 weeks ago
Selected Answer: B
Last paragraph from 19.2 Managing a stage boundary is not used towards the end of the final management stage unless there is a need to create an exception plan. This is because the activities to review the performance of the whole project, as part of the closing a project process, include reviewing the performance of the final management stage.
upvoted 1 times
...
Sniperone
2 years ago
A is Correct not B
upvoted 2 times
...
[Removed]
2 years, 7 months ago
B is Correct: Managing a stage boundary is not used towards the end of the final management stage unless there is a need to create an exception plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago