Exam PRINCE2-Foundation topic 1 question 373 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 373
Topic #: 1
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence.
The number of management stages for a project is defined by using the '[ ? ]' step of the recommended approach to planning.

  • A. designing a plan
  • B. defining and analysing the products
  • C. preparing a schedule
  • D. documenting a plan
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
Reference:
https://opentextbc.ca/projectmanagement/chapter/chapter-3-the-project-life-cycle-phases-project-management/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 2 years, 7 months ago
A is the correct answer. It should be Designing a Plan. Ref 9.3.1.1 Designing a plan
upvoted 5 times
...
skillfulsatellite
Most Recent 1 month, 1 week ago
Selected Answer: A
In the context of PRINCE2, the number of management stages for a project is defined during the "designing a plan" step. This step involves defining the stages required to manage the project effectively, considering the scope, complexity, and risk factors. Each stage should be structured to allow for adequate control and decision-making, ensuring the project progresses smoothly and can be controlled within agreed tolerances.
upvoted 1 times
...
Examcollectorthanos
1 month, 2 weeks ago
A is correct Why the other options are not correct: B. defining and analysing the products: This step focuses on identifying and understanding the project's outputs (products), not the number of stages. C. preparing a schedule: This step involves creating the detailed schedule of activities within each stage, but the number of stages is decided earlier in the planning process.
upvoted 1 times
...
AlinaHusanu
1 year, 3 months ago
Designing a plan A is correct
upvoted 1 times
...
MEHREEN1985
2 years, 1 month ago
9.3.1.1 Designing a plan A is correct
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago