Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 267 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 267
Topic #: 1
[All PRINCE2-Foundation Questions]

In which process does the project manager monitor the work assigned to a team manager?

  • A. Controlling a stage
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Managing product delivery
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
A; Why the other options are less suitable: B. Directing a project: This process is about the project board's overall guidance and authorization, not the detailed monitoring of work packages.   C. Managing a stage boundary: This process focuses on the transition between stages, not the day-to-day monitoring within a stage. D. Managing product delivery: This process is about accepting completed products from teams, not the ongoing monitoring of their work.
upvoted 1 times
...
Ppp333
1 year, 2 months ago
Selected Answer: A
17.1 Purpose Planned risk responses need to be actioned, their effectiveness monitored and corrective action taken where responses do not match expectations.
upvoted 1 times
Ppp333
1 year, 2 months ago
Correction: The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.
upvoted 1 times
...
...
ameli8222
1 year, 7 months ago
Selected Answer: A
In PRINCE2, the process where the project manager monitors the work assigned to a team manager is called "Managing a Stage Boundary". This process is part of the "Controlling a Stage" process, which is one of the seven processes in the PRINCE2 framework.
upvoted 1 times
...
[Removed]
2 years, 6 months ago
D is correct Ref:18.1
upvoted 2 times
...
roby
2 years, 6 months ago
Selected Answer: A
The Project Manager does the directing, not the Team Manager which is responsible for product delivery only.
upvoted 1 times
roby
2 years, 6 months ago
https://prince2.wiki/processes/controlling-a-stage/#:~:text=The%20purpose%20of%20the%20Controlling,the%20stage%20remains%20within%20tolerance.
upvoted 1 times
...
roby
2 years, 6 months ago
the controlling*
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...