C is correct.
Authorize the work to be done -> Controlling a stage.
Accepts and checks Work Package from the Project Manager -> Managing Product Delivery.
section 18.2 work on products allocated to the team is authorized and agreed. I dont think is C as it is mentioned the planned products are delivered to expectations and within tolerance and answer C does not mention tolerance
Options B, C, and D are objectives of other PRINCE2 processes:
B refers to the objective of the 'Managing by Exception' process
C refers to the objective of the 'Quality Control' process
D refers to the objective of the 'Closing a Project' process.
The objective of the 'Managing Product Delivery' process in PRINCE2 is to control the link between the project manager and the team managers by placing formal requirements on accepting, executing, and delivering project work. Based on this, the correct option is A. To authorize the work package allocated to the team.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
KeanoD
Highly Voted 1 year, 10 months agoHaranp12
Most Recent 7 months, 3 weeks agoAdrienne
9 months, 2 weeks agoRznNsr
10 months, 2 weeks agomr_alok
1 year, 3 months agoAnapellicer
1 year, 3 months agoShiroKurtia
11 months, 2 weeks agoSGN63
1 year, 3 months agorenza
1 year, 4 months agoOridanDesta
2 years agoIsabaut
2 years, 1 month agoElise88
2 years, 1 month ago