Question #: 43
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is an objective of the 'managing product delivery' process?

  • A. To authorize the work package allocated to the team
  • B. To raise exception reports when tolerance is exceeded
  • C. To ensure that delivered products match expectations
  • D. To record any lessons to help later management stages
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KeanoD
Highly Voted 2 years, 2 months ago
Selected Answer: C
C is correct. Authorize the work to be done -> Controlling a stage. Accepts and checks Work Package from the Project Manager -> Managing Product Delivery.
upvoted 7 times
...
Haranp12
Most Recent 1 year ago
Selected Answer: A
section 18.2 work on products allocated to the team is authorized and agreed. I dont think is C as it is mentioned the planned products are delivered to expectations and within tolerance and answer C does not mention tolerance
upvoted 1 times
...
Adrienne
1 year, 2 months ago
Selected Answer: C
C is correct
upvoted 1 times
...
RznNsr
1 year, 3 months ago
Selected Answer: A
This is the 100% correct answer
upvoted 1 times
...
mr_alok
1 year, 8 months ago
C is the correct answer To authorise a work package is done in Controlling a Stage and is PM’s responsibility
upvoted 1 times
...
Anapellicer
1 year, 8 months ago
Selected Answer: A
Options B, C, and D are objectives of other PRINCE2 processes: B refers to the objective of the 'Managing by Exception' process C refers to the objective of the 'Quality Control' process D refers to the objective of the 'Closing a Project' process. The objective of the 'Managing Product Delivery' process in PRINCE2 is to control the link between the project manager and the team managers by placing formal requirements on accepting, executing, and delivering project work. Based on this, the correct option is A. To authorize the work package allocated to the team.
upvoted 1 times
ShiroKurtia
1 year, 4 months ago
there is no quality control process
upvoted 1 times
...
...
SGN63
1 year, 8 months ago
Selected Answer: C
C is the the right answer
upvoted 2 times
...
renza
1 year, 9 months ago
Selected Answer: C
C is the the right answer since authorizing WP is the PM responsibility
upvoted 2 times
...
OridanDesta
2 years, 5 months ago
Selected Answer: A
the Authorization is a handshake between the Team manager and the Project manager in order to agree on te work package
upvoted 2 times
...
Isabaut
2 years, 6 months ago
Selected Answer: C
Planned products are delivered to expectations and within tolerance
upvoted 1 times
...
Elise88
2 years, 6 months ago
Selected Answer: C
It should be C To ensure that delivered products match expectations. Authorize a WP is controlling a stage
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...