D IS indeed correct;
A. Records the costs and timescales for delivery of the project's final product: This information is typically found in the project plan or stage plans.
B. Shows the dependencies between the project's products to aid planning: This is often shown in a Product Flow Diagram or a Product Breakdown Structure.
C. Provides a list of all the products to be delivered by the project: While the final deliverable is included, the Project Product Description focuses specifically on the criteria for accepting that final product.
C - Project product description: describes the project’s major products and intended
purpose, including the user’s quality expectations and the acceptance criteria and
acceptance methods for the project. It is created in the process of starting up a project
and refined during the process of initiating a project.
Gain agreement from the user on the what they want (project’s scope)
Define the customer’s quality expectations so the project can deliver a fit for purpose product
Define the acceptance criteria, method and responsibilities for the project.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week ago3578791
3 weeks, 2 days agoAnnie7799666
2 years, 6 months ago