Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 12 question 7 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 7
Topic #: 12
[All PRINCE2-Practitioner Edition 6 Questions]

The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Which 2 statements should be recorded under the Proximity heading?

  • A. Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project.
  • B. The risk of MFH having no outsourcing experience will be categorized as Stage 4 proximity.
  • C. Imminent risks are those which may occur within two weeks.
  • D. Any risk with a proximity category of imminent will be estimated as having a very high impact.
  • E. The risk of staff leaving the organization will be categorized as beyond the project proximity.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: AC
Statement A is correct because it defines the four categories of proximity that can be used to categorize risks in the project. Statement C is also correct because it defines imminent risks as those that may occur within two weeks. Statements B, D, and E are incorrect because they are not relevant or accurate in the given scenario. Statement B - there is no information in the scenario to support this statement. Statement D - the impact of a risk will depend on its specific characteristics. Statement E - this risk could occur during the project and would therefore be categorized as within the project
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Under the “Proximity” heading, the two statements that should be recorded are: Statement A: Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project. This statement defines the categories of proximity for this project, which is crucial for understanding when a risk might impact the project. Statement C: Imminent risks are those which may occur within two weeks. This statement provides a specific time frame for when risks categorized as “imminent” are expected to occur, which can help in prioritizing risk response strategies.
upvoted 1 times
ravi_aws
1 year, 1 month ago
Statement E does indeed categorize a specific risk, which is related to the proximity. However, the question asks for two statements to be recorded under the “Proximity” heading.
upvoted 1 times
...
...
ameyaengg
2 years, 2 months ago
Correct Answer : A & C
upvoted 2 times
...
GSD547
2 years, 7 months ago
Selected Answer: AC
A - This provides guidance on how proximity for risk events is to be assessed. Typical proximity categories will be imminent, within the stage, within the project, beyond the project. Ref. A.24.2. C - This is an acceptable definition for what is meant by an imminent proximity risk. Ref. A.24.2.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...